Order Process
Stage 1
Initial deposit of £750 + VAT to be paid at time of agreeing house design and signing contract.
2nd payment of £2250 + VAT to be paid prior to planning application submission.
Stage 2
3rd payment of £1250 + VAT upon instruction to proceed with warrant & engineering
4th payment (dependant on house type) to be paid prior to building warrant application submission.
Stage 3
Staged Payment 1 - 10% on instruction to commence manufacture
Staged Payment 2 - 35% 10 days prior to structural kit delivery
Staged Payment 3 - 30% 10 days prior to delivery of roughing kit
Staged Payment 4 - 25% 10 days prior to delivery of finishes
|